![]() |
OECD/NEA Rig of Safety Assessment (ROSA) ProjectThe OECD/NEA ROSA project aims to resolve issues in thermal-hydraulics analyses relevant to light water reactor (LWR) safety using the Japanese ROSA/LSTF facility. In particular, it intends to focus on the validation of simulation models and methods for complex phenomena that may occur during design basis events (DBE) and beyond-DBE transients.The key objectives of the OECD/NEA ROSA project are to:
When evaluating the safety of light water reactors, computer codes are used to simulate their behaviour during design basis events and beyond-DBE transients. This involves complex multi-dimensional single-phase and two-phase flow conditions, which can include non-condensable gas in many cases. Although current thermal-hydraulic safety analysis codes have a very high predictive capability (especially for one-dimensional phenomena such as flows in piping at high flow rates) there is a need for experimental work and code development and validation for these complex flow conditions. Given the increased use of best-estimate analysis methods in licensing, which is replacing traditional conservative approaches, the validation and quantification of uncertainties in the simulation models and methods is required. Many experimental facilities have contributed to the thermal-hydraulic databases available today. However, most of current data are insufficient for future codes that incorporate multi-dimensional simulation capabilities, mainly because the spatial resolution of measurement is not enough to assess the simulation models and methods. The ROSA project will seek to address these issues. The project consists of the following six types of ROSA large-scale experiments:
The programme contemplates a total of 12 tests, of which eight have been carried out so far. Four tests were performed in 2007, one on temperature stratification, one on water hammer and two on primary cooling through depressurisation. The remaining four tests were discussed by the project steering bodies, which defined the test initial and boundary conditions. They will be conducted in 2008 and in the first part of 2009. Project members also discussed the issues to be addressed in a possible follow up of the project, which is scheduled for completion in March 2009. Project participantsThe project is supported by safety organisations, research laboratories and industry from the following countries: Belgium, the Czech Republic, Finland, France, Germany, Hungary, Japan, Republic of Korea, Spain, Sweden, Switzerland, the United Kingdom and the United States.
Project periodApril 2005-March 2009 BudgetUS$ 1 million/year Related links
Last updated: 27 March 2007 |
||
Home - About Us - Work Areas - Data Bank - Publications - Press Room - List of acronyms - Search