OECD Nuclear Energy Agency / L'Agence pour l'énergie nucléaire OECD-OCDE

 

France

Nuclear power situation

National laws and regulations

Current issues and developments

Nuclear power situation

 
Number of nuclear units
connected to the grid
Nuclear electricity generation
(net TWh)
Nuclear percentage of total
electricity supply
France

59

428.7
78.1
OECD Europe
150
929.3
27.3
OECD TOTAL
346
(out of 437 worldwide)
2278.1
23.1
Source: Nuclear Energy Data 2007. The complete table for all OECD member countries is also available.

Nuclear Power Plants: Status and operations

The share of nuclear power in French electricity supply has reached its technical and economic maximum, amounting to about 63 000 MWe. It consists of 59 units, 58 being pressurised water reactors (34 at 900 MWe, 20 at 1 300 MWe, and four in the 1 450's) that were constructed by the French manufacturer FRAMATOME, and the 230 MWe fast breeder reactor, Phenix.


Nuclear plants accounted for 401 TWh in 2001 (over 75% of total electricity production), putting France as the world's second largest nuclear power producer. Table 1 lists the status of the power plants as of year-end 2001. Nuclear power generation represents about one-third of total primary energy supply and over 80% of the domestic energy production, making EDF by far the number one nuclear operator and the largest electricity producer in the world.

Table 1. Status of nuclear power plants

Station

Type

Net
capacity

Operator

Status

Reactor
supplier

Construction
date

Criticality
date

Grid
date

Commercial
date

Shutdown
date

BELLEVILLE-1

PWR

1310

EDF

Operational

FRAM

01-May-80

09-Sep-87

14-Oct-87

01-Jun-88

BELLEVILLE-2

PWR

1310

EDF

Operational

FRAM

01-Aug-80

25-May-88

06-Jul-88

01-Jan-89

BLAYAIS-1

PWR

910

EDF

Operational

FRAM

01-Jan-77

20-May-81

12-Jun-81

01-Dec-81

BLAYAIS-2

PWR

910

EDF

Operational

FRAM

01-Jan-77

28-Jun-82

17-Jul-82

01-Feb-83

BLAYAIS-3

PWR

910

EDF

Operational

FRAM

01-Apr-78

29-Jul-83

17-Aug-83

14-Nov-83

BLAYAIS-4

PWR

910

EDF

Operational

FRAM

01-Apr-78

01-May-83

16-May-83

01-Oct-83

BUGEY-2

PWR

910

EDF

Operational

FRAM

01-Nov-72

20-Apr-78

10-May-78

01-Mar-79

BUGEY-3

PWR

880

EDF

Operational

FRAM

01-Sep-73

31-Aug-78

21-Sep-78

01-Mar-79

BUGEY-4

PWR

880

EDF

Operational

FRAM

01-Jun-74

17-Feb-79

08-Mar-79

01-Jul-79

BUGEY-5

PWR

900

EDF

Operational

FRAM

01-Jul-74

15-Jul-79

31-Jul-79

03-Jan-80

CATTENOM-1

PWR

1300

EDF

Operational

FRAM

29-Oct-79

24-Oct-86

13-Nov-86

01-Apr-87

CATTENOM-2

PWR

1300

EDF

Operational

FRAM

28-Jul-80

07-Aug-87

17-Sep-87

01-Feb-88

CATTENOM-3

PWR

1300

EDF

Operational

FRAM

15-Jun-82

16-Feb-90

06-Jul-90

01-Feb-91

CATTENOM-4

PWR

1300

EDF

Operational

FRAM

28-Sep-83

04-May-91

27-May-91

01-Jan-92

CHINON-B-1

PWR

920

EDF

Operational

FRAM

01-Mar-77

28-Oct-82

30-Nov-82

01-Feb-84