![]() |
Slovak Republic
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Number of nuclear units connected to the grid |
Nuclear electricity generation (net TWh) |
Nuclear percentage
of total electricity supply |
|
| Slovak Republic |
5 |
14.1 |
54.9 |
| OECD Europe |
145 |
879.6 |
25.8 |
|
OECD TOTAL |
346 (out of 437 worldwide) |
2172.5 |
21.6 |
Source: Nuclear Energy Data 2008. The complete table for all OECD member countries is also available.
The decision on the orientation of the Slovak power industry in regard to the utilisation of nuclear power plants created in 1970s, was the result of the fact that useable reserves of primary energy resources could not meet the demand for electricity. The construction of the V-1 Bohunice plant (Nuclear Power Plants Bohunice (EBO) Units 1 and 2) both with the V-230 reactor type started in 1972 and the construction of the V-2 Bohunice plant (EBO Units 3 and 4) both with the V-213 reactor type in 1976.
Four nuclear units are in operation in Bohunice, and two in Mochovce with a total capacity of 2.2 GWe. In 1998 the units produced 11.4 TW h and the nuclear share of the electricity production in the Slovak Republic was 55.5% in 2005. The Slovak electric utility that operates the Bohunice nuclear power plant was established in 2002 through a restructuring of Slovenské Elektrárne, a.s. and renamed Slovenské Elektrárne (SE). Two of the Bohunice units are older Soviet-designed VVER-440/230 pressurised water reactors. After an extensive programme for upgrading these units carried out between 1991-2000, bringing them up to international safety standard levels, they are expected to operate until 2015. The two other Bohunice units are the more recently designed VVER-440/213 which incorporate most of safety features of non-Soviet-type reactors. A programme of further safety enhancement of these units has been undertaken in co-operation with Western European companies following the recommendations of the Slovak safety authority and the IAEA, mentioned further in this section.
Based on studies for the further development of nuclear power in the former CSFR and following a lengthy decision making process, the construction of another nuclear power plant with four VVER 440 units, with V-213 type reactors on the Mochovce site (Nuclear Power Plants Mochovce (EMO) Units 1 to 4), started in April 1981. With regard to conceptually non-clarified questions of the automatic control of production processes and nuclear safety, the completion of Unit 1, which was originally planned for 1985, has been gradually postponed and the completion process was not finished on time.
Based on a decision by the Slovak government, the first phase Mochovce Unit 1 was completed in 1998 and Unit 2 in 2000. For the completion of Units 1 and 2, contracts have been signed with the following organisations: Atomenergoexport; Electricité de France; Energoprojekt Prague; EUCOM (Siemens AG, Framatome SA); Hydrostav Bratislava; SKODA Prague; VÚJE Trnava; and Zarubezhatomenergostroj. The Slovak government took over the guarantees for bank loans for the completion of Mochovce Units 1 and 2.
Table 1 presents some basic operating data and Table 2 shows the status of nuclear power plants in the Slovak Republic. The costs of one MW h delivered from EBO 1, 2, 3 and 4 and EMO 1, are calculated including a 10% contribution to the State Fund for Decommissioning of Nuclear Power Installations.
Table 1. Basic Data Of Operating Nuclear Power Plants
| Unit | Production in TW h 2001 | Load Factor in % | Net Efficiency in % | Own electr. cons. in % | Prod. Loss in TW h | Heat delivered in TJ | ||
| 2001 | From commiss. till 31.12.01 |
Annual |
Cumulative |
Since commissioning |
2001 | 2001 | ||
| EBO 1 | 2,624 | 61,855 | 67,1 | 70,1 | 28,02 | 7,945 | 1,231 | 95 |
| EBO 2 | 3,150 | 60,717 | 81,1 | 72,7 | 28,55 | 7,603 | 0,705 | 165 |
| EBO 3 | 2,914 | 50,558 | 75,2 | 77,0 | 29,03 | 7,232 | 0,935 | 799 |
| EBO 4 | 3,020 | 48,705 | 78,1 | 78,2 | 29,00 | 7,114 | 0,834 | 754 |
| EMO 1 | 2,630 | 9,340 | 68,35 | 68,91 | 29,34 | 8,36 | 1,227 | 148 |
| EMO 2 | 2,761 | 5,647 | 71,65 | 71,97 | 29,04 | 8,13 | 1,093 | 144 |
| Total | - | - | ||||||
| Prod. Loss EMO (gross) = P+U+O, TWh according to WANO PI | P - planned | U - unplanned | O - other | Cumulative Loss |
| EMO 1 | 0,890 | 0,074 | 0,263 | 1,227 |
| EMO 2 | 0,651 | 0,208 | 0,234 | 1,093 |
These costs are approximately half compared with the costs of the coal-burning steam power plants in the Slovak Republic. The costs of fossil plants represent more than SKK 1000 per one MW h delivered on average. From the total electricity generated in the Solvak Republic in 2005, nuclear power plants generated 55.5%.
Table 2. Status of Nuclear Power Plants
| Station | Type | Capacity | Operator | Status | Reactor Supplier | Construction Date | Criticality Date | Grid Date | Commercial Date | Shutdown Date |
| BOHUNICE-1 | VVER | 408 | EBO | Operational | AEE | 01-Apr-74 | 27-Nov-78 | 17-Dec-78 | 01-Apr-80 | 31-Dec-06 |
| BOHUNICE-2 | VVER | 408 | EBO | Operational | AEE | 01-Apr-74 | 15-Mar-80 | 26-Mar-80 | 01-Jan-81 | |
| BOHUNICE-3 | VVER | 408 | EBO | Operational | SKODA | 01-Dec-76 | 08-Aug-84 | 20-Aug-84 | 14-Feb-85 | |
| BOHUNICE-4 | VVER | 408 | EBO | Operational | SKODA | 01-Dec-76 | 02-Aug-85 | 09-Aug-85 | 18-Dec-85 | |
| MOCHOVCE-1 | VVER | 388 | EMO | Operational | SKODA | 01-Oct-83 | 09-Jun-98 | 04-Jul-98 | 13-Oct-98 | |
| MOCHOVCE-2 | VVER | 388 | EMO | Operational | SKODA | 01-Oct-83 | 01-Dec-99 | 20-Dec-99 | 11-Apr-00 | |
| MOCHOVCE-3 | VVER | 388 | EMO | Construction Postponed | SKODA | 01-Jan-85 | ||||
| MOCHOVCE-4 | VVER | 388 | EMO | Construction Postponed | SKODA | 01-Jan-85 | ||||
| A-1 BOHUNICE | HWGCR | 110 | EBO | Under Decommissioning | SKODA | 01-Jan-58 | 01-Jan-72 | 01-Oct.-72 | 01-Dec-72 | 17-May-79 |
Reactor Type V-1
2x440 MW VVER V-230
Based on recommendations from the IAEA and EU experts, the "small backfitting" of V-1 was carried out between 1991 and 1992, at a cost of SKK 2 million, and mainly focused on:
The implementation of these actions was a prerequisite for the operation of the V-1 plant until 1995. According to the Slovak Republic Nuclear Regulatory Authority (ÚJD SR) Decision No.1/94, the prerequisite for further operation after 1995 was to implement a "gradual upgrading" programme between 1996-2000 at a cost of SKK 8 billion. The content of the gradual upgrade was as follows:
The implementation of the gradual upgrading was completed in line with the schedule approved by the ÚJD SR. The V-1 nuclear safety programme thus achieved the level acceptable for early nuclear power plants according to both the IAEA and WENRA reviews. During negotiations on Slovak accession to the EU, the Slovak government agreed to close the V-1 unit 1 in 2006 and the V-1 unit 2 in 2008.
Reactor Type V-2
EBO - 2 x 440 MW VVER 213
A similar programme will be implemented with the objective to upgrade V-2 seismic resistance and nuclear safety, focused mainly on:
The ultimate goal for V-2 is to establish conditions for extending its life up to 40 years, until 2025.
EMO - 2 x 440 MW VVER 213
The ÚJD SR issued operating licenses for the Mochovce Units 1 and 2.
Figure 1 shows the structure of institutions involved in the Slovak nuclear power sector.

The main domestic producer and supplier of selected components for nuclear power plant pressure systems (separators, piping) is the Slovak Power Engineering Works (SES) in Tlmace and the Piping Company in Kosice. The supplier of civil construction works is Hydrostav Bratislava.
The main foreign suppliers are Atomenergoexport (Russia), SKODA and EGP (Czech Republic). The well-known Western firms (EdF and Framatome) co-operated with the Slovak Republic during the Mochovce completion and the Bohunice upgrading.
The owner of the Bohunice and Mochovce plants is the utility Slovak Electric (SE). The operators of these six units are SE affiliates Nuclear Power Plants Bohunice (EBO) and Nuclear Power Plants Mochovce (EMO). EBO have built their own technical and professional capacities for the performance of maintenance activities. Specialised activities are ordered by EBO and EMO from manufacturers of certain components, or from specialised firms. The training of nuclear personnel, namely operators, maintenance and decommissioning personnel, is carried out by the training center in the VÚJE Trnava, Inc.'s - Engineering, Design and Research Organisation. VÚJE performs the professional, practical and theoretical training of nuclear power plant personnel in six categories based on the Certificate No. 1/94 from the ÚJD SR. Category 1 is designed for selected personnel, for example operators, control physicists and reactor unit supervisors. Following successful graduation from the theoretical and practical training, trainees obtain certificates. For the performance of certain functions, Category 1 personnel have to obtain a ÚJD license that has to be renewed every two or three years depending on the function.
All the fuel for the operation of the six VVER-440 units in Slovakia has been fabricated in the Russian Federation and delivered by a monopolist Russian supplier. The supplier takes care of the provision of natural uranium, its conversion and enrichment. No diversification is currently planned in the procurement of new fuel for the needs of the Slovak nuclear sector.
Newer generation VVER-440/213 units at Bohunice V-2 and Mochovce have been converted to use advanced fuel with higher enrichment (3.82%) and higher burn-up qualities (the fuel will stay in the reactor for about five years). This will result in a reduction of annual consumption of fuel to 84 assemblies (10 tU/year). Fuel storage on plant sites is maintained at the level corresponding to six month operation at the rated power level.
By the end of 2000, the six Slovak VVER-440 units had produced 7 300 spent fuel assemblies. Of this amount, approximately 700 assemblies were exported to the Russian Federation, 1 200 were cooled down in pools adjacent to the reactors, and 5 400 pieces were stored in a wet interim spent fuel storage facility at the Bohunice site. This facility was extensively refurbished during 1997-2000. The refurbishment resulted also in a capacity increase from 5 000 to 14 000 fuel assemblies (or 1 680 tU). This capacity is sufficient for the fuel storage needs of both Bohunice (until its expected closure) and of Mochovce until 2015. By this time, it will be necessary to build a new storage facility at the Mochovce site. Current intentions are that the facility will be based on dry storage technology.
The fundamental conception for back end fuel cycle management remains unchanged. It is still expected that spent fuel will be ultimately disposed of, in a deep underground geological repository. Activities on the selection of an adequate site are continuing.
The total amount of radioactive waste from the past operation of the Bohunice units is currently stored temporarily on site. The concepts of radioactive waste management, from nuclear power installations and other organisations using sources of ionisation radiation, were prepared in 1993. The following production process fixing facilities have been constructed or are currently being built:
All low- and medium-level radioactive waste from Bohunice will be stored in fiber-concrete containers. To make the system of radioactive waste management complete, it was necessary to commission the operation of a disposal facility for low- and medium-level radioactive waste at the Mochovce site in 2000.
A new plant at the SE utility, the Decommissioning of Nuclear Power Installations and Management of Radioactive Waste and Spent Fuel (SE-VYZ), commenced activities on 1 January 1996. The new plant is located on the site of the Bohunice nuclear power plants. Its field of activities is spread over the whole of Slovakia. It will be responsible for the ultimate disposal of all kinds of radioactive waste and spent fuel that have been and will be produced in the Slovak Republic, from the operation and decommissioning of nuclear power plants, as well as for early and complete preparation of designs and facilities for the execution of the above mentioned activities. Besides this, the new plant will provide the disposal of institutional radioactive waste from other organisations. The plant activities will be financed from the budget of the SE utility and from the State Fund for Decommissioning of Nuclear Power Installations and Management of Spent Fuel and Radioactive Waste. This fund was established in 1995. The money has been accumulated from contributions resulting from a 10% contribution from the selling price of electricity, paid by nuclear power plants. The payment of this contribution is the responsibility of the nuclear power plant owner. From this fund, it is possible to take finances for the preparation and decommissioning of nuclear power installations, and for the management of spent fuel and radioactive waste related to nuclear power installation decommissioning, provided that approval from the Board of the State Fund for Decommissioning is given.
According to the projected electricity supply from nuclear power plants in Slovakia, the contributions to the State Fund for Decommissioning of Nuclear Power Installations and Management of Spent Fuel and Radioactive Waste should provide approximately SKK 30.8 billion by 2010 including an interest rate of 6%. This amount should be sufficient according to calculations performed for the following work to be carried out: the construction of a long-term spent fuel storage installation with the costs of approximately SKK 4.2 billion; the decommissioning of the V-1 plant following the completion of its economic life (about 10.0 billion Sk); and for other investment actions in the field. The establishment of the State Fund for Decommissioning of Nuclear Power Installations and Management of Spent Fuel and Radioactive Waste should advance to a state where the decommissioning of nuclear power installations and management of radioactive waste is assured by its finances without any additional demands on the state budget of the Slovak Republic or other sources of SE.
For additional information on the Slovak Republic's radioactive waste management programme please see the OECD Nuclear Energy Agency's Radioactive Waste Management Programmes in OECD/NEA Member Countries.
The goal of the Slovak Republic's nuclear research and development complex is to establish a research and development basis for the state authorities, manufacturers and suppliers of process equipment for nuclear power installations as well as for nuclear power plant operators. Regarding its structure, it includes basic research which is concentrated in the Slovak Academy of Sciences and to a lesser extent in universities, and applied research to a larger extent including the activities of independent research institutes (share-holding companies and companies with limited responsibilities) and sections of industrial organisations (see Table 3).
Regarding financial aspects, the applied research is ensured by:
In the field of international co-operation, the most significant nuclear co-operation is: with the International Atomic Energy Agency (IAEA) in Vienna; with the European Union within the PHARE programs and the 6th Framework Program (EURATOM); and bilateral co-operation with international institutions and organisations. Slovakia co-operates through the IAEA with other countries on subjects such as:
International co-operation with the EU goes within the framework of research and development programs of the European Community focused mainly on the 5th Framework Program and PHARE programs. The PHARE programs in the field of nuclear safety relating to the EU are co-ordinated by the Slovak Ministry of the Economy.
The Nuclear Regulatory Authority of the Slovak Republic (ÚJD SR) is a participant in discussions on regional and national programmes in the field of nuclear safety. The national projects in this field, have been addressed since 1993 as regional ones in order to use the funds more effectively.
Table 3. Slovak Technical Support Organisations in the Nuclear Sector
| Institution Name | Headquarters | Number of employees | Area of activity | ||||||
| 1992 | 1993 | 1994 | 1995 | 1998 | 2000 | 2001 | |||
| VÚJE Trnava | Trnava | 543 | 462 | 434 | 420 | 612 | 633 | 612 | Nuclear Safety, in-service inspection, plant commissioning and operation, personnel training, radiation safety |
| Research Institute of Welding (VUZ) | Bratislava | 545 | 392 | 368 | 347 | 349 | 336 | 330 | Welding technology, equipment and materials, preparation of personnel, in-service inspections-only partly for nuclear power plants |
| Research Institute of Cables and Insulating Materials (VUKI) | Bratislava | 235 | 202 | 202 | 188 | 163 | 125 | 125 | Cables with reduced flammability radiation-resistant cables, testing of cables, residual life time of cables |
| Power Equipment Research Institute (VÚEZ) | Levice | 118 | 109 | 106 | 106 | 150 | 146 | 146 | Tests of containments, sealing, condensation systems, safety system design, filtration and ventilation |
| Power Research Institute (EGU) | Bratislava | 86 | 76 | 35 | 35 | 35 | 28 | 25 | Integrity and lifetime of RPV, tubes, antiseismic upgrading, thermal loading, economical aspects |
| Institute of Clinical and Preventive Medicine-Dept. of Hygiene of Radiation | Bratislava | 28 | 30 | 30 | 30 | 11 | 11 | 9 | Personal dosimetry, radiation monitoring, protective barriers, radon, protection of patient and personal in medicine |
| CSA and EBO | Trnava | 25 | 30 | 32 | 27 | 32 | 26 | 25 | 3-D model database of nuclear facilities, structural analysis digital archives |
| National Institute of Hygiene and Epidemiology (NUHE) Dept. for radiation protection | Bratislava | 25 | 24 | 23 | 24 | 22 | 23 | 22 | Expertise for radiation protection, state supervision in the field of radiation protection and nuclear safety |
| DECOM | Trnava | 8 | 12 | 15 | 15 | 20 | 22 | 22 | Preliminary projects for decommissioning, radioactive waste management decontamination |
| VUPEX | Bratislava | 23 | 9 | 8 | 6 | 7 | 5 | 8 | Technical-economical studies |
| RELKO | Bratislava | - | 6 | 6 | 10 | 10 | 10 | Reliability analysis, PSA studies, impact of external events | |
| ALLDECO | Trnava | 12 | 14 | 14 | 17 | 22 | 30 | 37 | Decontamination technology and equipment |
| MERIT | Trnava | 2 | 4 | 6 | 6 | 4 | 2 | 2 | Radiation protection, dosimetry, monitoring, calculations of radiation fields |
| Institute of Radioecology | Kosice | not avail. | 20 | 15 | 15 | 6 | 1 | 0 | Radiological impact on environment, releases, decontamination |
| TOTAL | 1650 | 1393 | 1297 | 1242 | 1443 | 1398 | 1373 | ||
The bases for bilateral co-operation are intergovernmental agreements, of which some have been transformed to reflect the the status of Slovakia as an independent state. Bilateral co-operation has been widely developed, and examples include:
A-1 Bohunice:
V-1 Bohunice:
V-2 Bohunice:
Mochovce:
For additional information on national laws and regulations concerning nuclear power please see the OECD Nuclear Energy Agency's Analytical Study of Nuclear Legislation in OECD countries.
The Nuclear Regulatory Authority (ÚJD) of the Slovak Republic was established in 1993 as an independent state regulatory body which reports directly to the government and is directed by a chairperson appointed by the Government. It is responsible for regulation and supervision of nuclear energy (mainly concerning the safety of nuclear installations, radioactive waste management and transportation of nuclear materials).
The ÚJD is also responsible for issuing authorisations for the siting, design, construction, importation, commissioning, operation and reconstruction of nuclear installations and their decommissioning. The governing regime for the different stages of service life of a nuclear installation has been strengthened by the Atomic Act adopted on 9 September 2004.
The results of a survey carried out in Slovakia concerning the public opinion of the use of nuclear energy are shown in figure 2. The data is based on the results of a standard survey by Gallup questionnaire on a selected sample of 1 037 people from the population above 18 years in 1995. Approximately 46% of the selected population indicated that they were in favour of nuclear power and approximately 44% were against.

Appendix 1 - International, Multilateral and Bilateral Agreements
Nuclear facts and figures for OECD countries
Number of nuclear units connected to the grid; Nuclear electricity generation (net TWh); Nuclear percentage of total electricity supply.
IEA energy statistics: Slovak Republic
Data available in the following areas: Coal, oil and gas use; Electricity production, supply and consumption; Heat production, supply and consumption; Graphs of sectorial final consumption by source in 1973 and 2001.
The Decommissioning and Dismantling of Nuclear Facilities in OECD/NEA Member Countries: Slovak Republic
This compilation of national fact sheets is intended to serve as an authoritative source of reference information on individual NEA member countries. In this context, the term "nuclear facility" includes all facilities associated with the production of nuclear power, from mining of uranium, through fabrication of nuclear fuel, nuclear power plant operation, fuel reprocessing and waste management, including related R&D facilities, and research and demonstration reactors.
Nuclear Legislation in OECD Countries: Slovak Republic
Regulatory and Institutional Framework for Nuclear Activities
Each country profile in this valuable reference work provides a detailed review of a full range of nuclear law topics. These include: the general regulatory regime, including mining; radioactive substances and equipment; nuclear installations; trade in nuclear materials; radiation protection; radioactive waste management; non-proliferation and physical protection; transport; and nuclear third party liability.
Energy for a Changing World
A website of the European Commission Directorate-General for Energy and Transport.
Nuclear Energy Data
Nuclear Energy Data is the NEAs annual compilation of essential statistics on electricity generation and nuclear power in OECD countries. The reader will have quick and easy reference to the status of and projected trends in total electricity generating capacity, nuclear generating capacity, and actual electricity production, as well as to supply and demand for nuclear fuel cycle services.
Last updated: 20 June 2007
Home - About Us - Work Areas - Data Bank - Publications - Press Room - List of acronyms - Search