CSNI0004 LEIBSTADT/STP-2001. (Abstract last modified 15-NOV-1989)
1.
NAME OR DESIGNATION - LEIBSTADT/STP-2001. 2.
COMPUTER FOR WHICH PROGRAM IS DESIGNED AND OTHER MACHINE VERSION PACKAGES AVAILABLE -
To request or retrieve programs click on the one of the active versions below.
A password and special authorization is required. Explanation of the status codes.
Machines used:
Package-ID Orig.Computer Test Computer
CSNI0004/01 Many Computers
3.
DESCRIPTION OF TEST FACILITY - The Leibstadt Nuclear Power Station is equipped with a direct cycle boiling water reactor belonging to the General Electric BWR product line BWR/6. The MARK III containment system encloses the nuclear island. The nuclear system is provided with a 238-inch internal diameter vessel and the core is built up of 648 fuel elements and 84 control rods. Each fuel bundle consists of 62 fuel rods and 2 water rods in an 8 x 8 array. The rated power of the Leibstadt BWR is 3012 MWt and it is designed for a net power of 942 MWe. 4.
DESCRIPTION OF TEST - The purpose of the test STP-2001 which occurred on 15 October 1984 was to demonstrate the capability of the Reactor Core Isolation Cooling (RCIC) system to maintain the reactor water level above level 1 (-337 cm) following a total loss of feedwater with the HPCS system unavailable. The test was initiated by tripping the two operating feedwater pumps. The HPCS was prevented from initiating automatically. 5.
EXPERIMENTAL LIMITATIONS OR SHORTCOMINGS - Plant description information is limited due to proprietary nature of plant design. 6.
PHENOMENA TESTED - The observed phenomena in this test is the liquid level decrease. 7.
SPECIAL FEATURES OF EXPERIMENT - The analysis of off-normal events in actual nuclear plants can be particularly valuable with respect to scaling and simulation problems and with regard to thermal-hydraulic nuclear feedback. 8.
COUNTERPART EXPERIMENTS - 9.
STATUS 10.
REFERENCES - 11.
TEST DESIGNATION - STP-2001 12.
PROGRAMMING LANGUAGE(S) USED - 15.
ESTABLISHMENT - 16.
MATERIAL AVAILABLE - 17.
CATEGORIES - Keywords: DATA, REACTOR COOLING SYSTEMS
Program-name Package-ID Status
LEIBSTADT/STP-2001 CSNI0004/01 Arrived
CSNI0004/01: 15-NOV-1989 Arrived, no report
1. M. Andreani
Leibstadt Nuclear Power Plant: Main System Data and Start-up
Tests STP-2001 and STP-25 test data
TM-42-88-20, August 17, 1989
CSNI0004/01:
CSNI0004/01:
LEIBSTADT NUCLEAR POWER PLANT
Reports prepared by:
Paul Scherrer Institute
Wurenlingen and Villigen
CH-5232 Villigen PSI
SWITZERLAND
CSNI0004/01:
CCVM data listing Time histories lists and graphs (GETARS) CVMLS
- Y. Integral Experiments Data, Databases, Benchmarks
Home - About Us - Work Areas - Data Bank - Publications - Press Room - List of acronyms - Search